Question: Activity Immediate Predecessor Duration (Weeks) A 8 B 12 A 7 D A 8 E B.C 1 F B.C 4 G DE 6 H DE

Activity Immediate Predecessor Duration (Weeks) A

Activity Immediate Predecessor Duration (Weeks) A 8 B 12 A 7 D A 8 E B.C 1 F B.C 4 G DE 6 H DE 2.5 H 5 J F G 2 K JI 8 a a. Construct a PERT/CPM network for this project and determine the critical path. b. How long will it to complete this project