Question: Consider a project with the activities durations and precedence relations depicted in the table below Activity Immediate Predecessor Duration, weeks A - 3 B A
Consider a project with the activities durations and precedence relations depicted in the table below Activity Immediate Predecessor Duration, weeks A - 3 B A 4 C A 2 D B, C 6 E C 5 F C 3 G E 7 H E, F 5 I D, G, H 8 (a) Draw the network diagram and attach it here. Please only submit .png, .jpg, .jpeg or .pdf file formats. NO HEIC