Question: Activity Immediate Predecessor Normal Time ( weeks ) # Possible Crashes Crash Cost Per Week J - 1 0 1 1 7 5 K J

Activity Immediate Predecessor Normal Time (weeks) # Possible Crashes Crash Cost Per Week
J -101175
K J 8245
L J 5260
M K 4220
N L 6255
P M, N 52265
Q P 7170
Y P 8235
Z Q 6195