Question: Activity Immediate Predecessor Optimistic Most Probable Pessimistic A 3 4 5 LO 00 A 3 5 7 A 4 5 6 D A N 3

Activity Immediate Predecessor Optimistic Most
Activity Immediate Predecessor Optimistic Most
Activity Immediate Predecessor Optimistic Most Probable Pessimistic A 3 4 5 LO 00 A 3 5 7 A 4 5 6 D A N 3 5 E B 6 10 14 F B B 8 13 G c 10 15 20 H D UT co 11 1 E 6 8 10 FGH 8 10 12 7 Which activity has the most slack? 8. What is the probability that this project will take more than 35 weeks? (Use 4 decimal places