Activity Immediate Predecessor Optimistic Time

Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time 1 6 10 14 2 1 0 1 2 3 1 16 20 30 4 2 3 5 7 5 4 N 3 4 6 3 N 10 13 7 4,6 1 N 3 8 7 0 2 4. 9 3,7 2 2 2 10 9 2 3 4 11 5,8 0 1 N 12 10,11 1 2 3 1. There are two critical paths in this network. One of the critical paths is 2. The other critical path is 3. The duration is 4. The EF at node 7 is 5. The LS at node 4 is