Question: Activity Immediate Predecessor Optimistic Time (O.T.) Most likely Time (M.T.) Pessimistic Time (P.T.) A None 4 6 9 B A 3 5 7 C A

Activity

Immediate

Predecessor

Optimistic Time

(O.T.)

Most likely Time

(M.T.)

Pessimistic Time

(P.T.)

A

None

4

6

9

B

A

3

5

7

C

A

4

7

12

D

B

4

8

10

E

C

5

9

15

F

D

4

4

5

G

D, E

3

6

8

H

F

5

6

10

I

G

5

8

11

J

H, I

5

5

5

Use both the longest path method and ES/EF; LS/LF method on the diagram for the following questions and show your answers in the table below.

What is the expected project completion time? What are the critical activities? What are the slack values for non-critical activities?

The Longest Path Method

ES/EF/LS/LF

Expected project finish time

Critical activities

Non-critical activities

(slack values)

- Calculate the probability that the project will be completed in 40 weeks.

-Calculate the probability that the project will be completed in 43 weeks.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!