Question: Use the table to answer the questions below: Activity Immediate Predecessor Optimistic Time (O.T.) Most likely Time (M.T.) Pessimistic Time (P.T.) A None 4 6

  1. Use the table to answer the questions below:

Activity

Immediate

Predecessor

Optimistic Time

(O.T.)

Most likely Time

(M.T.)

Pessimistic Time

(P.T.)

A

None

4

6

9

B

A

3

5

7

C

A

4

7

12

D

B

4

8

10

E

C

5

9

15

F

D

4

4

5

G

D, E

3

6

8

H

F

5

6

10

I

G

5

8

11

J

H, I

5

5

5

-Calculate the expected time for each activity

-Calculate the variance for each activity

-Using the information put together a network diagram

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!