Question: Use the table to answer the questions below: Activity Immediate Predecessor Optimistic Time (O.T.) Most likely Time (M.T.) Pessimistic Time (P.T.) A None 4 6
- Use the table to answer the questions below:
| Activity | Immediate Predecessor | Optimistic Time (O.T.) | Most likely Time (M.T.) | Pessimistic Time (P.T.) |
| A | None | 4 | 6 | 9 |
| B | A | 3 | 5 | 7 |
| C | A | 4 | 7 | 12 |
| D | B | 4 | 8 | 10 |
| E | C | 5 | 9 | 15 |
| F | D | 4 | 4 | 5 |
| G | D, E | 3 | 6 | 8 |
| H | F | 5 | 6 | 10 |
| I | G | 5 | 8 | 11 |
| J | H, I | 5 | 5 | 5 |
-Calculate the expected time for each activity
-Calculate the variance for each activity
-Using the information put together a network diagram