Question: Activity Immediate Predecessor Time A -- 8 B -- 6 C -- 4 D A 3 E C 5 F A 4 G B,D,E 2

Activity

Immediate Predecessor

Time
A -- 8
B -- 6
C -- 4
D A 3
E C 5
F A 4
G B,D,E 2

1. What is the completion time of the project?

2. What is the critical path ?

3. What is the earliest start of the activity D ?

4. What is the Latest finish of the activity B?