Question: Problem : A small software development project has seven major activities with known activity times (in weeks) as follows: Activity Immediate Predecessor Time A --

Problem: A small software development project has seven major activities with known activity times (in weeks) as follows:

Activity

Immediate

Predecessor

Time

A

--

4

B

--

3

C

A

2

D

B

7

E

C, D

4

F

B

5

G

E, F

4

  1. Draw the network neatly.
  2. Calculate the EF, LF, and slack value for each node.
  3. What is the Project Completion Time?
  4. Specify the Critical Path and Critical Activities.