Question: Problem : A small software development project has seven major activities with known activity times (in weeks) as follows: Activity Immediate Predecessor Time A --
Problem: A small software development project has seven major activities with known activity times (in weeks) as follows:
| Activity | Immediate Predecessor | Time |
| A | -- | 4 |
| B | -- | 3 |
| C | A | 2 |
| D | B | 7 |
| E | C, D | 4 |
| F | B | 5 |
| G | E, F | 4 |
- Draw the network neatly.
- Calculate the EF, LF, and slack value for each node.
- What is the Project Completion Time?
- Specify the Critical Path and Critical Activities.