Question: Activity Immediate Predecessor Time . B A 4 C A 2 D A 2 E B 7 F 5 G E, F 9 H F

Activity Immediate Predecessor Time . B A 4 C A 2
Activity Immediate Predecessor Time . B A 4 C A 2
Activity Immediate Predecessor Time . B A 4 C A 2 D A 2 E B 7 F 5 G E, F 9 H F 4 D, G, H 6 Question 179 (0.5 points) Listen E Path A-B-E-G-I is critical True False Question 180 (0.5 points) Listen Path A-C-F-G-l is critical True False Question 181 (0.5 points) Listen Path A-C-F-H-I is critical True False Question 182 (0.5 points) Listen Path A-D- is critical True False