Question: Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 3 B . 2 5 D B 6 E CD 2 F D

Schedule the following activities using CPM:
Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 3 B . 2 5 D B 6 E CD 2 F D 3 G F 5 H EG 4 b. What is the critical path? O A-C-E-F-G-H A-B-D-F-G-H A-C-E-H O A-C-E-G-H c. How many weeks will it take to complete the project? Number of weeks d. Which activities have slack, and how much? C. 9 weeks: E. 6 weeks. B. 1 week: D. 3 weeks. E, 1 week: H. 4 weeks