Question: Activity Immediate Predecessor Time in Days A None 3 B A 2 C A 1 D B and C 3 E D 4 What is

Activity Immediate Predecessor Time in Days
A None 3
B A 2
C A 1
D B and C 3
E D 4
What is the Latest Finish Time for the last activity in this project (i.e., the total time to complete the project)?