Question: Activity Immediate Predecessor (Time Weeks) A - 1 B A 4 C A 4 D B 2 E C, D 5 F D 2 G

Activity Immediate Predecessor (Time Weeks)
A - 1
B A 4
C A 4
D B 2
E C, D 5
F D 2
G F 2
H E, G 3

How many weeks will it take to complete the project?

Identify critical path

Which activities have slack, and how much?