Question: Activity Immediate Predecessor Time (Weeks) A 12 B 9 C A 5 D A, B 4 E C, D 8 F E 10 G F
Activity Immediate Predecessor Time (Weeks) A 12 B 9 C A 5 D A, B 4 E C, D 8 F E 10 G F 7 a. What is the expected completion time of the critical path? [ Select ] weeks. b. How much slack is there in activity D.? [ Select ] weeks c. What is the Late Start Late Finish for activity B.? [ Select ] d. How much slack is there in activity B.? [ Select ] e. What