Question: Problem 5-8 (Algo) Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 3 B A 2 C A 5 D B 6
Problem 5-8 (Algo)
Schedule the following activities using CPM:
| ACTIVITY | IMMEDIATE PREDECESSOR | TIME (WEEKS) |
|---|---|---|
| A | 3 | |
| B | A | 2 |
| C | A | 5 |
| D | B | 6 |
| E | C, D | 2 |
| F | D | 3 |
| G | F | 5 |
| H | E, G | 4 |
What is the critical path?
- multiple choice 1
A-B-D-F-G-H
A-C-E-H
A-C-E-G-H
A-C-E-F-G-H
How many weeks will it take to complete the project?
Which activities have slack, and how much?
- multiple choice 2
B 1 week D 3 weeks.
E 1 week H 4 weeks.
C 9 weeks E 6 weeks.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts