Question: Activity Immediate Predecessors (a) 3 (m) 6 (b) 8 A B A 5 8 10 PROJECT 4 A 6 8 D 1 2 4 B,

Activity Immediate Predecessors (a) 3 (m) 6 (b) 8

Activity Immediate Predecessors (a) 3 (m) 6 (b) 8 A B A 5 8 10 PROJECT 4 A 6 8 D 1 2 4 B, C D E 7 11 17 F D 7 9 12 D 6 8 9 H 3 4 7 F, G E, F, H I 3 5 7 1-mal Ksi (f) What are the expected time and the variance of the project? [2 marks] What is the probability the project will be completed in less than 32 weeks? [2 marks] What time should be set such that there is a 95% chance of completion? [2 marks]