Question: Activity Immediate Predecessor(s) A B C A D C E A,B F D G D,E H F,G Activity Duration (weeks) A 5 B 9 C
| Activity | Immediate Predecessor(s) |
| A | |
| B | |
| C | A |
| D | C |
| E | A,B |
| F | D |
| G | D,E |
| H | F,G |
| Activity | Duration (weeks) |
| A | 5 |
| B | 9 |
| C | 5 |
| D | 12 |
| E | 12 |
| F | 4 |
| G | 5 |
| H | 12 |
Calculate the earliest start/earliest finish, latest start/latest finish, and slack for each activity. Indicate them in a form of a network diagram.