Question: Consider a project whose activities are listed in the table below. Activity D will have slack time as long as... Activity Immediate Predecessors None A

Consider a project whose activities are listed in

Consider a project whose activities are listed in the table below. Activity D will have slack time as long as... Activity Immediate Predecessors None A B None A D B E C, D F E G E a. Duration of D Duration of A+ Duration of C d. Duration of D