Question: Activity Immediate Predecessor(s) ABCDEFG B A, D E, F This exercise contains only parts b, c, and d. b) The critical activities for the
Activity Immediate Predecessor(s) ABCDEFG B A, D E, F This exercise contains only parts b, c, and d. b) The critical activities for the leadership training program development project are c) The project length for the leadership training program development project = days. d) Slack time for each of the activities is: Activity A B C Slack Time Time (days) 353369 10 10
Step by Step Solution
There are 3 Steps involved in it
b To identify the critical activities for the leadership training program development project we nee... View full answer