Question: Activity Immediate predecessors Activity time (t) 8 2 3 60 A B D E F G H I J K L A A A B

Activity Immediate predecessors Activity time (t) 8 2 3 60 A B D E F G H I J K L A A A B D E, F G H, I J K 60 2 2 20 10 10 12 3 3 a) Draw a network for this project b) Determine the critical path c) Determine the earliest and latest activity times d) Determine slack time for each activity