Question: Draw the AON network for the following project and answer the questions that follow. Determine ES, EF, LS, LF, and slack for each activity and
Draw the AON network for the following project and answer the questions that follow. Determine ES, EF, LS, LF, and slack for each activity and then determine the total project completion time and the critical path for the project.
Activity | Immediate predecessors | Time (days) |
A | - | 5 |
B | - | 3 |
C | A, B | 2 |
D | B | 4 |
E | C, D | 5 |
f | E | 2 |