Question: Activity Immediate Predecessor/s Duration (Days) A B C D E F G H - - - A,B,C A,C D,E C, D F, G 5 6
| Activity | Immediate Predecessor/s | Duration (Days) |
| A B C D E F G H | - - - A,B,C A,C D,E C, D F, G | 5 6 5 7 9 5 8 11 |
Based on the information above
1.What is the slack for activity E
2. Late finish for activity for C
3. Critical path is?
4.You will receive a bonus of R4000,for everyday you complete the project within 30 days or you will looses R2000 for every project that takes more than 30days.Will you receive a penalty of bonus and if so how much?
5.D is an example of?