Question: Activity Immediate Predecessor/s Duration (Days) A B C D E F G H - - - A,B,C A,C D,E C, D F, G 5 6

Activity

Immediate Predecessor/s

Duration (Days)

A

B

C

D

E

F

G

H

-

-

-

A,B,C

A,C

D,E

C, D

F, G

5

6

5

7

9

5

8

11

Based on the information above

1.What is the slack for activity E

2. Late finish for activity for C

3. Critical path is?

4.You will receive a bonus of R4000,for everyday you complete the project within 30 days or you will looses R2000 for every project that takes more than 30days.Will you receive a penalty of bonus and if so how much?

5.D is an example of?