Question: Activity Immediate Predecessors Estimated Duration A ---- 6 B ---- 2 C, A 6 D A 8 E B 8 F B 10 G C,E
| Activity | Immediate Predecessors | Estimated Duration |
| A | ---- | 6 |
| B | ---- | 2 |
| C, | A | 6 |
| D | A | 8 |
| E | B | 8 |
| F | B | 10 |
| G | C,E | 4 |
| H | F | 6 |
Draw the CPM Network
What is the critical path
What will the scheduled (earliest completion) time for the entire project be?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts