Question: Given the activities whose sequence is described by for the following table, draw the appropriate activity - on - arrow ( AOA ) network diagram.
Given the activities whose sequence is described by for the following table, draw the appropriate activityonarrow AOA network diagram.
ACTIVITY IMMEDIATE PREDECESSORS TIMEDAYS
A
B A
C A
D B
E B
F C
G EF
H D
I GH
a Which activities are on the critical path?
b What is the length of the critical path?
a Critical path is ACFGI
b Time days
a Critical path is ACFGI
b Time days
a Critical path is BCFGI
b Time days
a Critical path is ACFGI
b Time days