Question: Activity Immediate Predecessors Expected time (a+4m+b)/6 Variance A (6 + 4(8) + 9)/6 = 7.83 .25 B (9 + 4(12) + 15)/6 = 12.00 1.00

Activity

Immediate Predecessors

Expected time

(a+4m+b)/6

Variance

A

(6 + 4(8) + 9)/6 = 7.83

.25

B

(9 + 4(12) + 15)/6 = 12.00

1.00

C

A, B

(4 + 4(6) + 11)/6 = 6.50

1.36

D

B

(3 + 4(4.5) + 6)/6 = 4.50

.25

E

A

(1 + 4(2) + 3)/6 = 2.00

.11

F

C

(1 + 4(3) + 5)/6 = 3.00

.44

G

E, F

(5 + 4(6) + 10)/6 = 6.50

.69

H

D, F

(2 + 4(3) + 4)/6 = 3.00

.11

I

G, H

(1 + 4(1) + 1)/6 = 1.00

.00

J

I

(2 + 4(3) + 7)/6 = 3.50

.60

1) draw the activity network for the problem.

2) Determine the activity schedule (ES, EF, LS, and LF) as well as slack.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!