Question: Activity Immediate Predecessors Expected time (a+4m+b)/6 Variance A (6 + 4(8) + 9)/6 = 7.83 .25 B (9 + 4(12) + 15)/6 = 12.00 1.00
| Activity | Immediate Predecessors | Expected time (a+4m+b)/6 | Variance |
| A | (6 + 4(8) + 9)/6 = 7.83 | .25 | |
| B |
| (9 + 4(12) + 15)/6 = 12.00 | 1.00 |
| C | A, B | (4 + 4(6) + 11)/6 = 6.50 | 1.36 |
| D | B | (3 + 4(4.5) + 6)/6 = 4.50 | .25 |
| E | A | (1 + 4(2) + 3)/6 = 2.00 | .11 |
| F | C | (1 + 4(3) + 5)/6 = 3.00 | .44 |
| G | E, F | (5 + 4(6) + 10)/6 = 6.50 | .69 |
| H | D, F | (2 + 4(3) + 4)/6 = 3.00 | .11 |
| I | G, H | (1 + 4(1) + 1)/6 = 1.00 | .00 |
| J | I | (2 + 4(3) + 7)/6 = 3.50 | .60 |
1) draw the activity network for the problem.
2) Determine the activity schedule (ES, EF, LS, and LF) as well as slack.