Question: Activity Immediate Predecessors Normal Crash NT (Weeks) NC ($) CT (Weeks) CC ($) A - 4 $200 2 $650 B A 6 500 4 900
| Activity | Immediate Predecessors | Normal | Crash | ||
| NT (Weeks) | NC ($) | CT (Weeks) | CC ($) | ||
| A | - | 4 | $200 | 2 | $650 |
| B | A | 6 | 500 | 4 | 900 |
| C | A | 5 | 600 | 3 | 1200 |
| D | A | 6 | 1000 | 5 | 1400 |
| E | B | 6 | 1500 | 5 | 2000 |
| F | C,D | 5 | 200 | 4 | 400 |
| G | E,F | 6 | 600 | 4 | 1200 |
Determine the minimum cost-schedule for this project to be completed in 18 weeks.?