Question: Activity Immediate Predecessors Normal Time (days) Crash Time (days) Normal Cost ($) Crash Cost ($) A - 4 2 200 500 B - 3 3
Activity Immediate Predecessors Normal Time (days) Crash Time (days) Normal Cost ($) Crash Cost ($) A - 4 2 200 500 B - 3 3 300 300 C A,B 6 2 800 1200 D - 4 3 400 600 F D 8 5 1000 1600
Consider the precedence chart given below. Give the sequence of crashing for 5 days. Compute the extra cost incurred because of crashing by 5 days.
show working steps