Question: Activity Immediate Predecessors Normal Time (days) Crash Time (days) Normal Cost ($) Crash Cost ($) A - 4 2 200 500 B - 3 3

Activity Immediate Predecessors Normal Time (days) Crash Time (days) Normal Cost ($) Crash Cost ($)
A - 4 2 200 500
B - 3 3 300 300
C A,B 6 2 800 1200
D - 4 3 400 600
F D 8 5 1000 1600

Consider the precedence chart given below. Give the sequence of crashing for 5 days. Compute the extra cost incurred because of crashing by 5 days.

show working steps