Question: Activity Immediate predecessors Normal time (days) Crash time (days) Normal cost Crash cost Crash cost per day A - 4 3 1000 1300 300 B
| Activity | Immediate predecessors | Normal time (days) | Crash time (days) | Normal cost | Crash cost | Crash cost per day |
| A | - | 4 | 3 | 1000 | 1300 | 300 |
| B | - | 7 | 4 | 1400 | 2000 | 200 |
| C | - | 5 | 4 | 2000 | 2700 | 700 |
| D | A | 6 | 5 | 1200 | 1400 | 200 |
| E | B | 3 | 2 | 900 | 1100 | 200 |
| F | C | 11 | 6 | 2500 | 3750 | 250 |
| G | D, E | 4 | 3 | 800 | 1450 | 650 |
| H | F, G | 3 | 1 | 300 | 500 | 100 |
Crash this project for five days at the least cost. Explain why you select the crash activity/ies for each day that the project is crashed. For each stage (day) that the project is crashed, fill out the following table. If more rows are needed, please add them manually.