Question: Activity Immediate predecessors Normal time (days) Crash time (days) Normal cost Crash cost Crash cost per day A - 4 3 1000 1300 300 B

Activity

Immediate predecessors

Normal time (days)

Crash time (days)

Normal cost

Crash cost

Crash cost per day

A

-

4

3

1000

1300

300

B

-

7

4

1400

2000

200

C

-

5

4

2000

2700

700

D

A

6

5

1200

1400

200

E

B

3

2

900

1100

200

F

C

11

6

2500

3750

250

G

D, E

4

3

800

1450

650

H

F, G

3

1

300

500

100

Crash this project for five days at the least cost. Explain why you select the crash activity/ies for each day that the project is crashed. For each stage (day) that the project is crashed, fill out the following table. If more rows are needed, please add them manually.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!