Question: Problem 3) (35 points) Draw the AON network for the following project and answer the questions that follow. Determine ES, EF, LS, LF, and slack
Problem 3) (35 points)
Draw the AON network for the following project and answer the questions that follow.
Determine ES, EF, LS, LF, and slack for each activity and then determine the total project completion time and the critical path for the project.
Crash this project to the maximum days it can be crashed at the least cost. Fill out the table for each day that the project is crashed.
| Activity | Immediate predecessors | Normal time (days) | Crash time (days) | Normal cost | Crash cost | Crash cost per day |
| A | - | 5 | 4 | 1000 | 1400 |
|
| B | - | 3 | 3 | 800 | - |
|
| C | A, B | 2 | 1 | 600 | 900 |
|
| D | B | 4 | 2 | 1600 | 2000 |
|
| E | C, D | 5 | 4 | 800 | 1200 |
|
| f | E | 2 | 1 | 1300 | 1400 |
|
| Stage | Critical path/s | Total project time before crashing | Crash activity/ies | Crash cost added | Total crash cost | Total project time |
| |
|
|
|
|
|
|
|
|
| |