Question: Activity Immediate Predecessors Normal Time ( weeks ) A - 8 B - 5 C A 3 D B 4 E C , D 6

Activity Immediate Predecessors Normal Time (weeks)
A -8
B -5
C A 3
D B 4
E C, D 6 The project will take [blank1] days to complete.