Question: ACTIVITY IMMEDIATE PREDECESSORS O M P A NONE 3 4 7 B NONE 5 7 12 C A 3 3 5 D B 1 1

ACTIVITY IMMEDIATE PREDECESSORS O M P

A NONE 3 4 7

B NONE 5 7 12

C A 3 3 5

D B 1 1 3

E B 3 1 4

F C,D 4 3 6

G E 3 1 2

H F,G 4 3 7

Using the PERT principle (in weeks)

What is the expected completion of time and the probability that the project will be completed within 20 weeks?