Question: ACTIVITY IMMEDIATE PREDECESSORS O M P A NONE 3 4 7 B NONE 5 7 12 C A 3 3 5 D B 1 1
ACTIVITY IMMEDIATE PREDECESSORS O M P
A NONE 3 4 7
B NONE 5 7 12
C A 3 3 5
D B 1 1 3
E B 3 1 4
F C,D 4 3 6
G E 3 1 2
H F,G 4 3 7
Using the PERT principle (in weeks)
What is the expected completion of time and the probability that the project will be completed within 20 weeks?