Question: Activity Immediate Predecessors Optimistic to Most Likely tm Pessimistic tp a none 8 10 12 b none 6 7 9 c b 3 3 3
| Activity | Immediate Predecessors | Optimistic to | Most Likely tm | Pessimistic tp |
| a | none | 8 | 10 | 12 |
| b | none | 6 | 7 | 9 |
| c | b | 3 | 3 | 3 |
| d | a | 10 | 15 | 20 |
| e | d | 6 | 7 | 8 |
| f | c | 9 | 10 | 11 |
| g | d | 5 | 7 | 10 |
| h | e, f | 14 | 15 | 16 |
a. Draw the network diagram
b. determine the earliest start, earliest finish, latest start and latest finish for the project
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
