Question: Activity Immediate Predecessors Optimistic to Most Likely tm Pessimistic tp a none 8 10 12 b none 6 7 9 c b 3 3 3

Activity

Immediate Predecessors

Optimistic to

Most Likely tm

Pessimistic tp

a

none

8

10

12

b

none

6

7

9

c

b

3

3

3

d

a

10

15

20

e

d

6

7

8

f

c

9

10

11

g

d

5

7

10

h

e, f

14

15

16

a. Draw the network diagram

b. determine the earliest start, earliest finish, latest start and latest finish for the project