Question: Activity Immediate Predecessor(s) Time Duration None 4 B None 3 A 2 D B 7 E C,D 5 F B 5 The number inside the

Activity Immediate Predecessor(s) Time Duration

Activity Immediate Predecessor(s) Time Duration None 4 B None 3 A 2 D B 7 E C,D 5 F B 5 The number inside the ending node in this AOA network should be