Question: Given the following information for an AOA network Immediate Activity Duration (days) Predecessor(s) A 4 none B 2. A C 7 none 4 A 5

Given the following information for an AOA

Given the following information for an AOA network Immediate Activity Duration (days) Predecessor(s) A 4 none B 2. A C 7 none 4 A 5 B,C,D How many critical activities are there in this AOA network