Question: Activity Immediate Predecessors Time (in weeks) A 3 B 4 C 2 D A 5 E B 3 F C 4 G D,E 2 H
Activity Immediate Predecessors Time (in weeks)
A 3
B 4
C 2
D A 5
E B 3
F C 4
G D,E 2
H E,F 2
I G 6
J H 5
The table above list the activity, immediate predecessors and the time each activity takes for a specific project. Draw the network and find the earliest, latest and slack times for these activities and state the critical path. How long does the project take to complete.