Question: Activity Immediate Predecessors Time Required (weeks) A Start 2 B Start 3 C A, B 2 D B 4 E C 3 F D, E
|
Activity | Immediate Predecessors | Time Required (weeks) |
| A | Start | 2 |
| B | Start | 3 |
| C | A, B | 2 |
| D | B | 4 |
| E | C | 3 |
| F | D, E | 2 |