Question: Activity Immediate Predecessors Time Required (weeks) A Start 3 B Start 4 C A, B 3 D B 5 E C 4 F D, E

Activity

Immediate

Predecessors

Time Required (weeks)

A

Start

3

B

Start

4

C

A, B

3

D

B

5

E

C

4

F

D, E

3

(d) Returning to the original project of parts (a) and (b), it has been determined that the task completion times for task C have the following distribution:

Time Required (weeks)

Probability

0.5

0.2

2

0.2

3

0.2

4

0.2

5

0.2

What is the corresponding distribution of project completion times?