Question: Activity Immediate Time Predecessor (Months) START A START 2 START 4 B C START 3 D A 3 E A 5 F 6 G C

Activity Immediate Time Predecessor (Months)

Activity Immediate Time Predecessor (Months) START A START 2 START 4 B C START 3 D A 3 E A 5 F 6 G C 4 H D 4 1 D 8 J B,E,F,1 2 K B,E,F,G, 3 END H,J,K 1. The critical path is 2. The duration is 3. The ES at node Jis 4. The EF at node K is 5. The LS at node B is