Activity Immediate Predecessor Time (Months)
START - -
A START 2
B START 4
C START 3
D A 3
E A 5
F C 4
G C 4
H D 4
I D 8
J B,E,F,I 2
K H,J,K 3
END H,J,K -

1. What is the critical path?

2. What is the duration?

3. What is the ES (Early Start) at node J?

4. What is the EF (Early Finish) at node K?

5. What is the LS (Late Start) at node B?

Hi, my subject is Operations Management and we were asked to do a network diagram. Thank you for helping me :D

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!