Question: Activity Immediate Time (Weeks) A - 8 B A 2 C A 6 D C 4 E B,D 3 F D 4 G E, F
| Activity | Immediate | Time (Weeks) |
| A | - | 8 |
| B | A | 2 |
| C | A | 6 |
| D | C | 4 |
| E | B,D | 3 |
| F | D | 4 |
| G | E, F | 6 |
a. What is the critical path?
A-C-D-F-G
A-C-D-E-G
A-B-D-F-G
A-B-E-G
b. How many weeks will it take to complete the project?
c. How much slack does activity B have?