Question: QUESTION THREE [25] Question 3.1. [15] Using the table provided below, calculate the late start of activity C. You are required to show all your

QUESTION THREE [25]

Question 3.1. [15]

Using the table provided below, calculate the late start of activity C. You are required to show

all your work (including a critical path diagram) and provide an explanation of each step in your

process to support your answer.

Activity

Predecessor

Duration

Duration
A None 5
B A 2
C A 6
D A 3
E D 1

3.2. Using the table provided below, calculate the early finish of activity D. You are required to

provide an explanation of how you reached the answer you have.

Activity

Predecessor

Duration

Duration
A None 5
B A 2
C A 6
D A 3
E B, C, D 1

3.3. Using the table provided below, calculate the duration of the critical path. You are required to provide an explanation of how you reached the answer you have.

Activity

Predecessor

Duration

Duration
A None 5
B A 2
C A 6
D A 3
E B,C, D 1

Question 3.2.

Identify key quality project plan steps that you feel should be included within a typical overall project plan. Be sure to include quality items throughout the project plan life cycle. (10)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!