Question: QUESTION THREE [25] Question 3.1. [15] Using the table provided below, calculate the late start of activity C. You are required to show all your
QUESTION THREE [25]
Question 3.1. [15]
Using the table provided below, calculate the late start of activity C. You are required to show
all your work (including a critical path diagram) and provide an explanation of each step in your
process to support your answer.
| Activity | Predecessor Duration | Duration |
| A | None | 5 |
| B | A | 2 |
| C | A | 6 |
| D | A | 3 |
| E | D | 1 |
3.2. Using the table provided below, calculate the early finish of activity D. You are required to
provide an explanation of how you reached the answer you have.
| Activity | Predecessor Duration | Duration |
| A | None | 5 |
| B | A | 2 |
| C | A | 6 |
| D | A | 3 |
| E | B, C, D | 1 |
3.3. Using the table provided below, calculate the duration of the critical path. You are required to provide an explanation of how you reached the answer you have.
| Activity | Predecessor Duration | Duration |
| A | None | 5 |
| B | A | 2 |
| C | A | 6 |
| D | A | 3 |
| E | B,C, D | 1 |
Question 3.2.
Identify key quality project plan steps that you feel should be included within a typical overall project plan. Be sure to include quality items throughout the project plan life cycle. (10)