Question: Activity K L N M ) Immediate Predecessor(s) None K K L N JM Q Q P Y, Z Normal time (weeks) 9 7 5

Activity K L N M ) Immediate Predecessor(s) None

Activity K L N M ) Immediate Predecessor(s) None K K L N JM Q Q P Y, Z Normal time (weeks) 9 7 5 4 6 6 8 8 6 Crashing Costs 1st week 2nd week $820 $830 $250 $90 $90 $600 $700 $100 $400 $450 $180 P Y Z End $170 $180 9 L 16 7 16 M 20 4 26 P 34 8 34 Z 40 6 20 Q 26 0 K 9 9 6 40 E 40 9 N 14 5 14 / 20 6 26 Y 34 8 How many paths are there in this diagram? (1 mark) 2 3 4 5 QUESTION 30 How many critical paths are there in the diagram? (2 marks) 0 1 3 4 QUESTION 31 What is the minimum number of weeks for this project to be completed? (2 marks) 32 36 40 42 OOoo