Question: Activity List for a Board Fence Project Under Predecessors, the following notation is used: x / #: Activity x must finish # days before this
Activity List for a Board Fence Project
"Under Predecessors, the following notation is used:
x#: Activity must finish # days before this activity can begin.
: The # of days after activity starts that this activity can begin.
This activity cannot finish until # days after is completed.
XSF#: This activity must finish # days before can start.
Draw the Precedence Diagram for the given projects and highlight the critical path. Determine the project total duration, ES EF LS LF and TF for each given activity.