Question: Activity name - duration - predecessors A - 4 - none B - 3 - a C - 4 - b D - 5 -

Activity name- duration- predecessors
A-4-none
B-3-a
C-4-b
D-5-b
E-8-c,d??
Determine the activities along the critical path as well as the total project duration |
A. critical path activities A,D,E total project duration 17 days
B. critical path activities a, cot d e total project duration 21 days
C. critical path activities A,b,e total project duration 15 days
D. critical path activities a,b,d,e total project duration 20 days
 Activity name- duration- predecessors A-4-none B-3-a C-4-b D-5-b E-8-c,d?? Determine the