Question: Activity Normal Cost Immediate Predecessor(s) A B Normal Time (weeks) 2 3 2 4 4 3 Crash Time (weeks) 1 1 1 3 2 2

Activity Normal Cost Immediate Predecessor(s) A B

Activity Normal Cost Immediate Predecessor(s) A B Normal Time (weeks) 2 3 2 4 4 3 Crash Time (weeks) 1 1 1 3 2 2 2 Total Cost with Crashing 22750 34000 27000 49000 58000 30500 84500 19000 22000 30000 26000 48000 56000 30000 80000 16000 D E A,B C DE F,G F G 5 H 2 1 a. What is the project completion date? Construct an AON network with ES, EF, LS, LF, slack time calculations. Show critical path b. What is the total cost required for completing this project on normal time? c. If you wish to reduce the time required to complete this project by 4 weeks, which activities should be crashed, and how much will this increase the total cost

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!