Question: Activity Normal Duration Crash Duration Crash Cost/Day A 10 8 $200 B 16 12 $400 12 9 $100 D 17 16 $250 E 14 13

Activity Normal Duration Crash Duration Crash

Activity Normal Duration Crash Duration Crash Cost/Day A 10 8 $200 B 16 12 $400 12 9 $100 D 17 16 $250 E 14 13 $300 F 6 4 $300 The project represented by this network diagram has activity lengths in days and per day crash costs as shown in the table. What is the cheapest crash cost for the project if the contractor must complete all work in 45 days? $1,150 O $950 $1,450 O $550