Question: Also which activity should be crashed second? B C D F PLease answer quickly for a thumbs up The project represented by this network diagram

Also which activity should be crashed second? B C

Also which activity should be crashed second?

B

C

D F

PLease answer quickly for a thumbs up

The project represented by this network diagram has activity lengths in days and crash costs as shown in the table. The contractor must complete all work in 45 days. Which activity must be crashed first? Activity Normal Duration Crash Duration | Crash Cost/Day 10 8 $250 16 12 $400 1129 $100 DT17 16 $300 $300 6 4 $350 MUA 14 13 2200 ) OB) E OCC OD) A