Question: Activity Normal duration Normal cost Crashed duration Crashed cost (days) ($) (days) ($) A 8 1500 5 2100 B 6 2000 3 3050 C 7

Activity Normal duration Normal cost Crashed

Activity Normal duration Normal cost Crashed duration Crashed cost (days) ($) (days) ($) A 8 1500 5 2100 B 6 2000 3 3050 C 7 1000 5 1600 A project is crashed so that A takes 6 days, B takes 3 days and C takes 6 days. What happens to project cost? a. It increases by $1750 b. It increases by $1350 C. We have to know the critical path to know if project cost will increase d. * It increases by $1400 e. It increases by $1700