Activity Normal time Crash time Normal cost Crash cost Predecessor A 4 3 2 2 0 0
Fantastic news! We've Found the answer you've been seeking!
Question:
Activity Normal time Crash time Normal cost Crash cost Predecessor
A
B
C
D A
E B
F C
G DE
What is the cost for crashing the project by days?