Question: Activity Normal Time ( days ) Normal Cost ( $ ) Crash Time ( days ) Crash Cost ( $ ) Immediate Predecessor ( s

Activity
Normal Time(days)
Normal Cost($)
Crash Time(days)
Crash Cost
($)
Immediate Predecessor(s)
A
5
800
4
1,000
B
5
1,100
2
2900
C
2
600
1
900
A, B
D
3
1,200
2
2000
B
E
3
1,500
2
1,700
C, D
F
2
1,300
1
1,400
E
G
3
900
3
900
E
H
5
500
2
800
G
Part 2
a. What is the project's duration if only normal times are used?
The project duration is
enter your response here
day(s).(Enter your response as an integer.)
Part 3
b. What is the minimum-cost schedule?
With the minimum-cost schedule, the project duration is
enter your response here
day(s).
(Enter
your response as an
integer.)
Part 4
c. What is the critical path for the minimum-cost schedule?
The critical path for the minimum-cost schedule is
A-C-E-F
B-D-E-F
B-C-E-G-H
B-C-E-F
A-C-E-G-H
B-D-E-G-H
.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!