Question: Activity Normal Time ( days ) Normal Cost ( $ ) Crash Time ( days ) Crash Cost ( $ ) Immediate Predecessor ( s
Activity
Normal Timedays
Normal Cost$
Crash Timedays
Crash Cost
$
Immediate Predecessors
A
B
C
A B
D
B
E
C D
F
E
G
E
H
G
Part
a What is the project's duration if only normal times are used?
The project duration is
enter your response here
daysEnter your response as an integer.
Part
b What is the minimumcost schedule?
With the minimumcost schedule, the project duration is
enter your response here
days
Enter
your response as an
integer.
Part
c What is the critical path for the minimumcost schedule?
The critical path for the minimumcost schedule is
ACEF
BDEF
BCEGH
BCEF
ACEGH
BDEGH
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock